The Use of BIM Application for Schedule Planning and Real of Costs Estimation in Promenade Bridge Construction Project, Taman Mini Indonesia Indah
DOI:
https://doi.org/10.35313/potensi.v27i2.5301Abstract
Scheduling and cost estimation are essential for successful construction projects, including the revitalization of Taman Mini Indonesia Indah and the Promenade Bridge development. To improve efficiency and effectiveness, this study applies Building Information Modeling (BIM), using Tekla Structures 2022 for 3D modeling and Quantity Take-Off. The model provides detailed volume data, which—alongside daily and weekly reports—is used for cost analysis and scheduling. BIM integration enables better visualization, planning, and resource management throughout the project lifecycle. The result of the study shows that the total Real of cost estimation of Rp13.136.571.631,44 with the duration of work based on an analysis of daily reports and weekly reports for 155 working days starting on January 6th, 2021 until May 21st, 2021. The use of Tekla Structures supports accurate modeling and work volume calculations, helping streamline budgeting and scheduling processes. The use of Building Information Modeling (BIM) in construction projects significantly accelerates the scheduling and cost estimation process even though certain limitations must be considered during project planning and execution.
Downloads
References
[1] X. Liu, J. Zhao, Y. Yu, and Y. Ji, “BIM-based multi-objective optimization of clash resolution: A NSGA-II approach,” J. Build. Eng., vol. 89, p. 109228, 2024.
[2] BIM PUPR, “Latar Belakang.” .
[3] J. Pantiga and A. Soekiman, “Kajian Implementasi Building Information Modelling (BIM) Di Dunia Konstruksi Indonesia,” Rekayasa Sipil, vol. 15, no. 2, pp. 104–110, 2022.
[4] Bina Marga, “Spesifikasi umum 2018,” Direktorat Jendral Bina Marga, vol. 2018, no. Revisi 3, pp. 1–6, 2018.
[5] Departemen Pekerjaan Umum Direktoral Jenderal Bina Marga, “Tata Cara Perencanaan Jembatan Penyeberangan untuk Pejalan Kaki di Perkotaan,” Departemen Pekerjaan Umum Direktoral Jenderal Bina Marga. p. 73, 1995.
[6] Pusat Litbang Jalan dan Jembatan, Pd 03 - 2017 - B Pedoman Perencanaan Teknis Fasilitas Pejalan Kaki. Kementerian PUPR, 2017.
[7] Direktorat Bina Program Jalan, Standar Jembatan Gelagar Komposit. Jakarta.
[8] Kementerian PUPR, Peraturan Menteri PUPR Nomor 1 Tahun 2022 Tentang Pedoman Penyusuanan Perkiraan Biaya Pekerjaan Konstruksi Bidang Pekerjaan Umum dan Perumahan Rakyat. Kementerian PUPR, 2022.
[9] M. A. Enshassi, K. A. Al Hallaq, and B. A. Tayeh, “Limitation Factors of Building Information Modeling (BIM) Implementation,” Open Constr. Build. Technol. J., vol. 13, pp. 189–196, 2019.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Potensi: Jurnal Sipil Politeknik

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
All papers published in Potensi: Jurnal Sipil Politeknik are under a CC-BY-SA or The Creative Commons Attribution-ShareAlike License.
All submitted papers must be original. Works that have been published are not under consideration for publication in other proceedings or scientific journals. Authors are responsible for obtaining all necessary permissions to reproduce tables, figures, and images. The paper must not contain defamation and must not violate any other rights of third parties.
Authors agree that the editorial board’s decision regarding the opportunity for paper presentation is final. Authors are prohibited from attempting to influence the technical team in efforts to have their paper published.
Before the final acceptance of the paper, authors are required to confirm in writing that they hold all copyrights to their paper and grant the publishing rights to Jurnal Potensi: Jurnal Sipil Politeknik.