Labor Productivity Disparities in the Planning and Implementation Phases

Authors

  • Aditya Rachmad Prasetyo Universitas Pembangunan Nasional “Veteran” Surabaya
  • I Nyoman Dita Pahang Putra Universitas Pembangunan Nasional “Veteran” Surabaya
  • Suliman Badawi Ahmed Kampala International University

DOI:

https://doi.org/10.35313/potensi.v27i2.6287

Keywords:

Labor Productivity, Planning Phase, Implementation Phase, Comparative analysis

Abstract

Infrastructure plays an important role in promoting connectivity, economic growth, and community welfare. In the construction sector, labor productivity is a crucial factor that determines project accomplishment. This study aims to analyze and compare the labor productivity during planning and implementation phase using secondary data as the main source. Data sources include a valid project documents and related regulation. The analysis carried out to find the planned labor productivity based on the cost budget plan and time schedule, the realized productivity value based on the cost budget plan and daily report, and the comparison between the two. The results showed that there was a significant variation in the labor productivity level between the planning and implementation phases of the project. There was an increase in labor productivity in several types of work including plastic cast installation 47%, D36-300 dowel installation 12%, 2-layer wiremesh 35%, Rigid Pavement K-350 28%, and joint filler work 71%. On the other hand, works such as flooring and tie-bar works experienced a decrease in labor productivity by 47% and 11%. These findings provide valuable insights for project management to improve future planning and execution, emphasizing the need for continuous labor productivity evaluation to achieve optimal result.

Downloads

Download data is not yet available.

References

[1]F. Yeremia, W. Robert, J. M. Mandagi, & P. A. K. Pratasis, “Analisis Pengaruh Percepatan Durasi terhadap Biaya Proyek Menggunakan Program Microsoft Project 2013 (Studi Kasus: Pembangunan Gereja GMIM Syalo’om Karombasan),” Jurnal Sipil Statik, vol. 3, no. 2, pp. 141–150, 2015. doi:https://ejournal.unsrat.ac.id/v2/index.php/jss/article/view/6870/6397

[2] B. A. Rumengan, T. T. Arsjad, & J. Tjakra, “Pemodelan Proporsi Sumber Daya Proyek Konstruksi Menggunakan Metode Regresi,” Jurnal Sipil Statik, vol. 7, no. 10, pp. 1275–1282, Oct. 2019, doi:https://ejournal.unsrat.ac.id/v2/index.php/jss/article/view/26043

[3] Y. Gusty Wibowo & A. Purnomo, “Analisis Produktivitas Tenaga Kerja pada Pekerjaan Mekanikal dan Elektrikal (Studi Kasus: Revitalisasi Gedung Kantor Cabang BNI Kelapa Gading, Jakarta),” Jurnal Teknik Sipil, vol. 16, no. 2, 2021. doi: https://doi.org/10.21009/jmenara.v16i2.20232

[4] C. M. Sujana & R. A. Hakim, “Perbandingan Produktivitas Tenaga Kerja Pembesian dan Bekisting pada Jam Kerja Normal dan Lembur Menggunakan Metode Productivity Rating,” Jurnal Rekayasa Konstruksi Mekanika Sipil, vol. 04, no. 2, pp. 145–52, Sep. 2021. url:https://ejournal.ust.ac.id/index.php/JRKMS/article/view/1400

[5] Kementerian Pekerjaan Umum dan Perumahan Rakyat, “Peraturan Menteri Pekerjaan Umum dan Perumahan Rakyat Nomor 1 Tahun 2022 tentang Pedoman Penyusunan Perkiraan Biaya Pekerjaan Konstruksi Bidang Pekerjaan Umum dan Perumahan Rakyat,” 2022. Available: https://peraturan.bpk.go.id/Details/216825/permen-pupr-no-1-tahun-2022

[6] Badan Standarisasi Nasional, “Standar SNI 7394:2008 – Tata Cara Perhitungan Harga Satuan Pekerjaan Beton untuk Konstruksi Bangunan Gedung dan Perumahan,” 2008. Available: https://bsn.go.id/

[7] N.P.I Yulianan & K.A.Suryawan, “Analisis Kebutuhan Sumber Daya Proyek Pada Pekerjaan Kayu Cabana, Screen Lobby, Penyekat Ruangan dan Pergola Drop Off berdasarkan Indeks Satuan Lapangan’, Potensi , vol. 24, no. 1, pp. 23–35, April. 2022. url: https://doi.org/10.35313/potensi.v24i1.2579

[8] N. D. Fitriani & M. Sitompul, “Perhitungan SDM Menggunakan Resource Leveling untuk Efisiensi Tenaga Kerja pada Pembangunan Pasar Baru Kabupaten Mandailing Natal,” Jurnal Media Teknik Sipil Samudra, vol. 2, no. 2, p. 1, Oct. 2021. url:https://ejurnalunsam.id/index.php/jmtss/article/download/3994/2855/

[9] N. Maelissa, W. Gaspersz, & S. Metekohy, “Dampak Pandemi COVID-19 bagi Pelaksanaan Proyek Konstruksi di Kota Ambon,” JURNAL SIMETRIK, vol. 11, no. 1, Jun. 2021. doi: https://doi.org/10.31959/js.v11i1.21

[10] G. Yanti, “Produktivitas Tenaga Kerja dengan Metode Work Sampling pada Proyek Perumahan di Kota Pekanbaru,” Jurnal Teknik Sipil Siklus, vol. 3, no. 2, pp. 100–106, Oct. 2017. doi: https://doi.org/10.31849/siklus.v3i2.385

[11] K. N. Baiti, Djumali, & E. Kustiyah, “Produktivitas Kerja Karyawan Ditinjau dari Motivasi, Disiplin Kerja, dan Lingkungan Kerja pada PT. Iskandar Indah Printing Textile Surakarta,” Edunomika, vol. 04, no. 01, pp. 69–87, 2020. doi: http://dx.doi.org/10.29040/jie.v4i01.812

[12] D. A. Prasetyo, Anthony, H. P. Chandra, & S. Ratnawidjaja, “Analisis Produktivitas Tenaga Kerja dengan Metode Work Sampling: Studi Kasus pada Proyek Tunjungan Plaza 6,” Jurnal Dimensi Prataman Teknik Sipil, vol. 6, no. 1, pp. 1–8, Feb. 2017. url:https://publication.petra.ac.id/index.php/teknik-sipil/article/view/5359]

[13] K. Septian Yuanto, H. Christavian, & S. Limanto, “Analisis Produktivitas Pekerja dengan Metode Work Sampling: Studi Kasus pada Proyek X,” Jurnal Dimensi Pratama Teknik Sipil, vol. 7, no. 2, pp. 185–192, Aug. 2018. url:https://publication.petra.ac.id/index.php/teknik-sipil/article/view/7706

[14] P. P. Indonesia, “Undang-Undang Republik Indonesia Nomor 13 Tahun 2003 tentang Ketenagakerjaan,” 2003. url: https://peraturan.bpk.go.id/Details/43013

[15] N. Kartika, S. M. Robial, & A. Pratama, “Analisis Produktivitas Tenaga Kerja pada Pekerjaan Kolom di Proyek Pembangunan Gedung Pemda Kabupaten Sukabumi,” Jurnal Momen, vol. 03, no. 2, pp. 103–112, 2020. doi: https://doi.org/10.35194/momen.v3i2.1207

[16] P. G. A. U. Wiratama, I. G. A. A. I. Lestari, & I. G. A. Diputera, “Kajian Perbandingan Produktivitas Tenaga Kerja Rencana dengan Produktivitas Tenaga Kerja Pelaksanaan pada Proyek Pembangunan Gedung Pengadilan Negeri Badung,” Jurnal Ilmiah Teknik UNMAS, vol. 4, no. 1, p. 14, Apr. 2024. url:https://jurnal.poliupg.ac.id/index.php/snp2m/article/view/350

[17] A. B. Pratama, “Faktor yang Mempengaruhi Produktivitas Tenaga Kerja Konstruksi di Bungku, Kabupaten Morowali, Sulawesi Tengah,” Prosiding Seminar Hasil Penelitian (SNP2M), pp. 155–159, 2017. doi: https://doi.org/10.24256/kelola.v2i2.440

[18] I. Ukkas, “Faktor-faktor yang Mempengaruhi Produktivitas Tenaga Kerja Industri Kecil di Kota Palopo,” Journal of Islamic Education Management, vol. 2, no. 2, pp. 187–198, Feb. 2017. url: https://publication.petra.ac.id/index.php/teknik-sipil/article/view/11752/10358

[19] M.A. Risanji, Raflis, “Analisis Faktor Pemeliharaan Bangunan Gedung Terhadap Kenyamanan Pekerja Kantor,” Potensi, vol. 20, no. 2, pp. 40–85, Okt. 2018. url: https://doi.org/10.35313/potensi.v20i2.1268

[20] D. Trisno, E. W. Secio, & S. Limanto, “Studi Awal pada Faktor yang Mempengaruhi Produktivitas Pekerjaan Konstruksi pada Bangunan di Surabaya dan Samarinda,” Jurnal Dimensi Pratama Teknik Sipil, vol. 10, no. 2, pp. 33–9, Aug. 2021. url: https://e-journal.unmas.ac.id/index.php/jitumas/article/view/8958

[21]M. Yuneta, A. A. K. S. Gobang, and Y. Putra, “Analisa Produktivitas Tenaga Kerja Di Lapangan Pekerjaan Dinding pada Proyek Pembangunan Penambahan Ruang Kelas Baru,” Jurnal Latar, vol. 2, no. 1, pp. 72–78, 2024. doi: https://doi.org/10.69749/jl.v2i1.67

Published

2025-10-14

How to Cite

Prasetyo, A. R., Putra, I. N. D. P., & Ahmed, S. B. (2025). Labor Productivity Disparities in the Planning and Implementation Phases. Potensi: Jurnal Sipil Politeknik, 27(2), 39–46. https://doi.org/10.35313/potensi.v27i2.6287

Most read articles by the same author(s)